1. The projected cost of the Mid-Currituck Bridge has more than doubled since federal approval in 2019.
  2. To date, $61 million has been spent on the Mid-Currituck Bridge project, without a construction contract.
  3. The funding gap for the bridge exceeds $700 million, under either delivery model.
  4. Toll revenues over 50 years cannot support project costs.
  5. NCDOT overestimated its traffic forecasts.
  6. The original financing plan is no longer viable under current conditions.
  7. The window to advance the Mid-Currituck Bridge project is narrowing.